We have recently made huge investments in improving infrastructure at Stamco Timber. We have been upgrading the racking to enhance safety across our site. And we also have an exciting new outfeed system in place. This impressive piece of machinery, which stacks & bundles timber, has been delivered to St Leonards all the way from Weinig in Germany.
Getting ready for this upgrade has taken months of planning by our team. In preparation for the outfeed system installation, we have had to remove old equipment, excavate a sizeable pit and concrete a new base. The outfeed system required both mechanical & electrical installation over a couple of weeks and we are pleased to report is all up and running successfully now.
Our Production Manager, Lee Watson, commented on the outfeed upgrade “It’s a million miles better than what we had before.”
Check out this time lapse video of how the process went!